Guildford council releases Wisley appeal timetable

The timetable for the appeal [APP/Y3615/W/16/3159894] by Wisley Property Investments in the matter of Guildford Borough Council's refusal of planning permission for "Outline planning permission for the phased development of a new settlement of up to 2,068 dwellings" [15/P/00012] at Three Farm Meadows, Hatch Lane, Ockham has been released to interested parties.

 

ACTION TIMETABLE
Start date 31 October 2016
Submission of questionnaire 14 November 2016
Deadline for comments from interested parties 12 December 2016
Submission of statement of case (Local Planning Authority) 27 January 2017
Pre-inquiry meeting 11 July 2017
Submission of proofs of evidence 8 August 2017
Submission of agreed statement of common ground 22 August 2017
Submission of agreed section 106 agreement and schedule of conditions 22 August 2017
Submission of rebuttals 29 August 2017

Witness names and anticipated duration for:

  • opening and closing statements;
  • evidence in chief;
  • cross-examination of other parties' witnesses; and
  • re-examination

Copy of LPA event notification letter

Inquiry date minus 3 weeks

29 August 2017

Inquiry

  • Time: 10:00
  • Date: 19 September 2017
  • Venue: TBC

Estimated number of sitting days

16

Report submitted to Secretary of State on or before

TBA

Decision issued on or before

TBA


2017 Guildford Local Plan

Guildford’s NEW local Plan has just opened for consultation. PLEASE RESPOND before 24th July 2017.  GGG has published its responses to Local Plan Policies here 


GGG Latest

Catch up on the latest news, issues and events from Guildford Greenbelt Group


Useful links

Find your way to the web sites of planning commentators, local residents' groups and much more